"Entergy Louisiana is building a $470 million, 60-mile transmission line to feed the site, but in a joint brief, a coalition opposing the project argued the data center could consume close to 20% of Louisiana's total electricity, warning of "costs that could ultimately exceed a billion dollars". A Bloomberg analysis found wholesale electricity prices for ratepayers within 50 miles of data centers have climbed as much as 276% over the past five years."
- rest of article at https://moneywise.com/news/top-stories/meta-zuckerberg-louisiana-hyperion-data-center-tax-break